Ark Data Centre
KIPO were responsible for designing a tier III data centre with the design of the medium voltage infrastructure and standby generation systems for 48MW.
Our Services and Solutions:
24 new 2.5mVA 11kV generators synchronised onto the SSE grid
Complex 11kV distribution systems, including hot standby controls, PMS and EMS systems
Short circuit and cable sizing calculations
Protection and Discrimination Studies
Infrastructure ducts and cable trenches
Substation designs, including switch room layouts, back up distribution, protection relay panels, alarms and controls
Lighting and emergency lighting systems external and internal
Security systems and UPS
PROJECT DETAILS
Client: Ark
Value: £15m
Sector: Data Centres